Decision Memo Completed

Pine Creek Basin Trailhead Toilet

Modoc National Forest Modoc, California Warner Mountain Ranger District

A new vault toilet at the Pine Creek Basin Trailhead is needed to provide sanitation facilities at this high-use recreation site. The District will install one (1) single-stall vault toilet at the trailhead.

Location

Pine Creek Trailhead, just west of the South Warner Wilderness, about 16 mi. SE of Alturas, CA.

Project timeline

1
Scoping Start
04/15/2021
2
Decision
07/2022 (Estimated)
3
Implementation
06/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Trail Management; Wilderness Management
Pine Creek Basin Trailhead ToiletDecision Signed Date: 07/25/2022
ForestsModoc National Forest
DistrictsWarner Mountain Ranger District
Legal Land DescriptionT. 41 N., R. 14 E., sec. 36, Mount Diablo Baseline and Meridian.
Recreation managementFacility management