Defensible Fuel Profile Zone (DFPZ), Group Selection (GS) in addition to, Wildland Urban Interface fuels reduction. Road reconstruction, decommissioning and construction, approx. 10-miles of temp road construction and subsequent decom.
Location
Approximately 4-11 miles northwest of Portola and 1-7 miles north of Graeagle.
Project timeline
1
Scoping Start
09/25/2010
2
Objection Period Start
01/19/2011
3
Decision
04/2011 (Estimated)
4
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface; Hfra Title Ii: Biomass |
| Notice and Comment Regulation | 218 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Jackson Project Environmental Assessment | Decision Signed Date: 04/12/2011 |
| Forests | Plumas National Forest |
| Districts | Beckwourth Ranger District |
| Legal Land Description | T22N, R11E; T22N, R12E; T23N, R11E; T23N, R12E. |