This project is operations, maintenance and management of recreation facilities owned by SFWP on NFS land
Location
Sly Creek Reservoir
Project timeline
1
Scoping Start
02/22/2012
2
Decision
04/2012 (Estimated)
3
Implementation
05/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Sly Creek Recreation Area Special Use Authorization Temporary 1 Yr. Renewal | Decision Signed Date: 04/16/2012 |
| Forests | Plumas National Forest |
| Districts | Feather River Ranger District |
| Legal Land Description | T20N, R8E, Sec.4, 5, 8, 9, 16, 17, 18, 19, 20 |