Excavation of 20' x 20' pit within the river channel. Processing of material through a power sluice. Larger boulders would be moved out of the river with a derrick and choker system. Duration of the plan would be 3 years.
Location
North Fork of the Feather River, southwest of Seneca and northeast of Belden, CA. Legal location T26N, R7E, SE 1/4 of Section 24, MDBM.
Project timeline
1
Scoping Start
12/15/2016
2
Comment Period
02/28/2018
3
Decision
04/2018 (Estimated)
4
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Partner Placer Mining Exploration | Decision Signed Date: 04/17/2018 |
| Partner Mining Exploration Project | Decision Signed Date: 04/17/2018 |
| Forests | Plumas National Forest |
| Districts | Mt. Hough Ranger District |
| Legal Land Description | T26N, R7E, Section 24, MDBM. |