These Emergency Relief for Federally Owned Roads (ERFO)funded projects would replace failed culverts with larger pipe and other water control improvements before repairing damaged roadbed with the existing travel ways to reestablish access.
Location
China Gulch, FSR 23N60, MP 8.95; Four Trees Sites 1 and 2, FSR 23N28, MP 14.5 and 15.3; Milsap Bar, FRS 23N60, MP 6.8; Ponderosa Way Sites 1 and 2, FSR 20N24, MP 2.85 and MP 2.87
Project timeline
1
Scoping Start
05/15/2018
2
Decision
07/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Watershed Improvements |
| 2018 Emergency Road Repairs | Decision Signed Date: 07/11/2018 |
| Forests | Plumas National Forest |
| Districts | Feather River Ranger District |
| Legal Land Description | Not Applicable |