Operators will excavate an area along the stream bench using a backhoe to dig three test trenches. Trenches are expected to be 30' x 3' x 2'. Material will be processed through a trommel using water pumped from West Branch Lights Creek.
Location
Legal location is T28N, R11E, Section 31, MDBM. The claim is located along the West Branch of Lights Creek, northeast of Greenville, CA.
Project timeline
1
Scoping Start
11/26/2018
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Four Kings Mining Exploration Project | Decision Signed Date: 06/24/2019 |
| Forests | Plumas National Forest |
| Districts | Mt. Hough Ranger District |
| Legal Land Description | Not Applicable |