Pacific Gas and Electric (PG&E) proposes to decommission segments of the de-energized Caribou-Palermo 115kV transmission line within the Plumas National Forest.
Location
The approximately 33-mile segment extends from Belden Forebay to Parkhill, within Plumas and Butte Counties, California.
Project timeline
1
Scoping Start
05/19/2021
2
Decision
05/2022 (Estimated)
3
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PG&E Caribou Palermo Line Decommissioning Project | Decision Signed Date: 05/20/2022 |
| Forests | Plumas National Forest |
| Districts | Feather River Ranger District |
| Legal Land Description | Not Applicable |