PG&E proposes to underground approximately 0.51 miles of the electric distribution facilities on the Big Bend 1102 Line. This action would be authorized under a special use.
Location
The power line is located along Milsap Bar Road (Butte County). The project site is located within the Plumas National Forest.
Project timeline
1
Scoping Start
11/05/2021
2
Decision
12/2021 (Estimated)
3
Implementation
12/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PG&E PN-003364 Big Bend Fire Rebuild Underground Line SU | Decision Signed Date: 12/06/2021 |
| Forests | Plumas National Forest |
| Districts | Feather River Ranger District |
| Legal Land Description | Not Applicable |