PG&E proposes to remove 40,000 cubic yards of material from the Chips Creek disposal site. The material had been stockpiled at the site by Cal Trans and consisted of rockslide materials over the course of many years.
Location
Chipps Creek and HWY 70 in the Feather River canyon
Project timeline
1
Scoping Start
02/24/2022
2
Decision
06/2022 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| PG&E Chipps Creek Mineral Materials Contract | Decision Signed Date: 06/14/2022 |
| Forests | Plumas National Forest |
| Districts | Mt. Hough Ranger District |
| Legal Land Description | T25N, R6E, SE of Section 23, Plumas County, California, Mount Diablo Base Meridian. |