Decision Memo Completed

Chico Seed Orchard IHC Work Center Construction Project

Plumas National Forest Butte, California Feather River Ranger District

This project proposes to build a new Work Center to house the Feather River Interagency Hotshot Crew (FRIHC) and one engine module displaced when the Brush Creek Work Center burned in the North Complex Fires, during 2021.

Location

The Chico Seed Orchard is located on 209 acres in Chico, California. Development started in 1904 when the site was assigned to the Agricultural Research Service for the purpose of plant breeding research and plant introduction from all over the world.

Project timeline

1
Scoping Start
04/29/2022
2
Decision
01/2023 (Estimated)
3
Implementation
01/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Chico Seed Orchard IHC Work Center Construction ProjectDecision Signed Date: 01/05/2023
ForestsMendocino National Forest; Plumas National Forest
DistrictsGrindstone Ranger District; Feather River Ranger District
Legal Land DescriptionNot Applicable
Facility management