Remove fuel loading, reforestation, herbicide preparation
Location
Volcano Units are on La Porte Road and the other units are located along the Mt. Hough Trail System.
Project timeline
1
Scoping Start
02/11/2022
2
Decision
03/2024 (Estimated)
3
Implementation
03/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Volcano Reforestation Project | Decision Signed Date: 03/06/2024 |
| Forests | Plumas National Forest |
| Districts | Mt. Hough Ranger District |
| Legal Land Description | Not Applicable |