Placement of a 13.6 mile fiber optic pole line within the PacifiCorp 115 kv transmission line corridor running parallel to the Gasquet Toll Road (Del Norte Cty Road 314 from Ore. border to Gasquet).
Location
UNIT - Smith River NRA, STATE - California, COUNTY - Del Norte
Project timeline
1
Scoping Start
08/17/2012
2
Comment Period
08/17/2012
3
Decision
10/2012 (Estimated)
4
Implementation
10/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Charter Communication Fiber Optic Line through the Smith River NRA | Decision Signed Date: 10/09/2012 Legal Notice Date: 03/21/2013 |
| Forests | Six Rivers National Forest |
| Districts | Gasquet Ranger District/Smith River NRA |
| Legal Land Description | T18N R3E HM, Sec 1, 2, 10, 11, 15, 21, 22, 28, 32 & 33, T17N R3E HM, Sec 5, 7, 8, 18, T17N R2E HM, Sec 12, 13, 21, 22, 23, & 24. |