Decision Memo Completed

Griffin Creek Culvert Replacement and County Road Paving

Six Rivers National Forest Del Norte, California Gasquet Ranger District/Smith River NRA

Replace current 30 inch pipe with 96 inch. Resurface and pave 3.25 miles on Del Norte roads 305, 314, 315, 316.

Location

Oregon Mt. Rd. (Del Norte Co. Rd. # 324) at Mile Post 1.94

Project timeline

1
Scoping Start
03/08/2013
2
Decision
06/2013 (Estimated)
3
Implementation
10/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Watershed Improvements
Griffen Creek Culvert Replacement and County Road PavingDecision Signed Date: 06/14/2013
ForestsSix Rivers National Forest
DistrictsGasquet Ranger District/Smith River NRA
Legal Land DescriptionT18N, R4E, Section 9
Road managementWatershed managementWildlife, fish, rare plants