Project activities are include road maintenance, such as: brushing, blading, grading, outsloping, spot rocking, culvert cleaning, slope stabilization, constructing water bars or rolling dips, replacing culverts, installing drop inlets, etc.
Location
Six Rivers National Forest All Units and the Klamath NF Ukonom Ranger District
Project timeline
1
Scoping Start
06/11/2013
2
Decision
07/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements |
| Forest-wide Road Maintenance | Decision Signed Date: 07/23/2014 |
| Forests | Klamath National Forest; Six Rivers National Forest |
| Districts | Orleans/Ukonom Ranger District; Six Rivers National Forest All Units |
| Legal Land Description | T5S-9N, T12N-14N, R4E-8E HB&M, T26N-28N, R11W-12W, MDB&M |