The Project would thin and commercially harvest trees and treat surface and ladder fuels up to 70 acres to maintain and expand the Mad Ridge Fuelbreak.
Location
Proposal includes five (5) units up to 70 acres total, along Mad River Rock Road (01N03) administered by the Mad River Ranger District.
Project timeline
1
Scoping Start
09/03/2018
2
Decision
11/2018 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Timber Sales (Green) |
| D70 Shaded Fuelbreak Maintenance and Expansion Project | Decision Signed Date: 11/20/2018 |
| D70 Shaded Fuelbreak Maintenance and Expansion | Decision Signed Date: 11/20/2018 |
| D70 Fuelbreak Project | Decision Signed Date: 11/20/2018 |
| D70 Shaded Fuelbreak Project | Decision Signed Date: 11/20/2018 |
| Forests | Six Rivers National Forest |
| Districts | Mad River Ranger District |
| Legal Land Description | T1N, R6E, sections 20, 28 and 29 |