Fuel reduction on 780 acres within the urban interface around the community of Pinecrest. Treatments would include thinning, pile burning, meadow and riparian restoration and manual noxious weed removal.
Location
Pinecrest
Project timeline
1
Scoping Start
02/29/2008
2
Objection Period Start
04/03/2009
3
Decision
05/2009 (Estimated)
4
Implementation
06/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Pinecrest Interior Healthy Forest Restoration | Decision Signed Date: 05/18/2009 |
| Forests | Stanislaus National Forest |
| Districts | Summit Ranger District |
| Legal Land Description | Sec 14-15, 21-23, 28-29 T4N R18E |