Decommission upper road and construct new route with a grade that will allow skiers easier and safer access to the lower runs. Base improvements include a helispot, conveyors, lifts and 4 test wells for snow making.
Location
Dodge Ridge Winter Sports Area
Project timeline
1
Scoping Start
12/14/2009
2
Comment Period
05/14/2010
3
Decision
06/2010 (Estimated)
4
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management |
| Dodge Ridge Upper Road and Base Improvements | Decision Signed Date: 06/23/2010 Legal Notice Date: 06/29/2010 |
| Forests | Stanislaus National Forest |
| Districts | Summit Ranger District |