The Pinecrest Campgrounds (47902) project replaced this project on September 30, 2015.
Location
Pinecrest Campground
Project timeline
1
Scoping Start
05/10/2012
2
Comment Period
03/2014 (Estimated)
3
Objection Period Start
07/2014 (Estimated)
4
Decision
10/2014 (Estimated)
5
Implementation
12/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management |
| Forests | Stanislaus National Forest |
| Districts | Summit Ranger District |
| Legal Land Description | Not Applicable |