Cal Net proposes to install a wireless telecommunications tower and 10 antennas at the project site.
Location
Located at approximately 1.7 miles northeast of the intersection of USFS Route 1S16 and Smith Station Road.
Project timeline
1
Scoping Start
05/06/2022
2
Decision
05/2022 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Smith Peak Communication Site Equipment Installation | Decision Signed Date: 05/06/2022 |
| Forests | Stanislaus National Forest |
| Districts | Groveland Ranger District |
| Legal Land Description | Not Applicable |