Review status and consistency of term summer home use permits and renew permits as found consistent. Includes summer home tracts along Metolius.
Location
Summer home tracts on the Metolius River
Project timeline
1
Scoping Start
06/21/2006
2
Decision
05/2008 (Estimated)
3
Implementation
02/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Metolius River Recreation Residence Special Use Permit Reissuance | Decision Signed Date: 05/28/2008 |
| Forests | Deschutes National Forest |
| Districts | Sisters Ranger District |
| Legal Land Description | T12S. R9E, Sec 34 and T13S, R9E, Sec 3, 10, 15 |