Improve riparian habitat and function by removing selected encroaching lodgepole pine, spot burning willow clumps, planting riparian-dependant vegetation and placing woody material in the stream channel.
Location
Spruce Creek between FS Road 5830 and the confluence with Hemlock Creek plus associated stringer meadows.
Project timeline
1
Scoping Start
09/08/2006
2
Comment Period
09/12/2007
3
Decision
12/2007 (Estimated)
4
Implementation
05/2008 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Watershed Improvements |
| 2007 Spruce Creek Riparian Rehabilitation | Decision Signed Date: 12/13/2007 |
| Forests | Deschutes National Forest |
| Districts | Crescent Ranger District |
| Legal Land Description | T25S, R07E, Sections 34 and 35; T26S, R07E, Sections 2 and 3 |