Project proposes to use a combination of commercial & non-commercial harvest, mowing, and underburning to restore and maintain fire dependent ecosystems & to maintain forest health. Project proposes to treat approximately 10,875 acres.
Location
High Desert
Project timeline
1
NOI in Federal Register
03/17/2008
2
DEIS NOA in Federal Register
07/31/2009
3
FEIS NOA in Federal Register
11/06/2009
4
Decision
10/2009 (Estimated)
5
Implementation
02/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Plan Amendment; Timber Sales (Green) |
| Deadlog Vegetation Management Project | Decision Signed Date: 10/25/2009 Legal Notice Date: 10/30/2009 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | T22S R15E; T23S R14E; T23S R15E |