Review status and consistency of term summer home special use permits adn renew permits found consistent. Includes summer homes on the shore of Elk Lake.
Location
The summer homes are located along the shore of Elk Lake
Project timeline
1
Scoping Start
06/21/2006
2
Decision
05/2008 (Estimated)
3
Implementation
02/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Elk Lake Recreation Residence Special Use Permit Re-issuance | Decision Signed Date: 05/19/2008 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | T18S, R8E, Sections 29 and 32 |