The Forest proposes to issue a Special Use Permit to the City of Bend. The purpose of the project is to authorize the City of Bend to upgrade the existing Bridge Creek intake facility and replace the City's aging Bridge Creek water supply pipelines.
Location
West of Bend, Ore., between the City's water intake and Outback Reservoir Site. Pipeline route is primarily along FSR 4601 and 4603.
Project timeline
1
Scoping Start
04/28/2011
2
Comment Period
03/29/2012
3
Decision
07/2012 (Estimated)
4
Implementation
08/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Special Use Permit: City of Bend Bridge Creek Water Supply System | Decision Signed Date: 07/10/2012 (FS Withdrawn) Legal Notice Date: 07/12/2012 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |