Environmental Assessment Completed

Eyerley Road Decommissioning Project

Deschutes National Forest Deschutes, Oregon Sisters Ranger District

About 38 miles of road would be decommissioned to protect resource values and reduce road maintenance costs.

Location

The project area is located about 20 miles north of Sisters, Oregon.

Project timeline

1
Scoping Start
06/23/2011
2
Comment Period
04/06/2012
3
Decision
05/2012 (Estimated)
4
Implementation
08/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning
Everly Roads Decommissioning ProjectDecision Signed Date: 05/16/2012 Legal Notice Date: 05/25/2012
ForestsDeschutes National Forest
DistrictsSisters Ranger District
Legal Land DescriptionT11S, T12S R10E
Road management