Bend Broadband proposes to install 4,300 feet of a buried fiber optic line adjacent to Meadow Camp off Hwy 46. This line would be within the right-of-way.
Location
from Road 4600-115 to Hwy 46, then west along highway for about 2800 feet; then 4600-120 for 300 feet.
Project timeline
1
Scoping Start
01/26/2012
2
Comment Period
04/13/2012
3
Decision
06/2012 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Bend Broadband Underground Fiber Optic Line Installation | Decision Signed Date: 06/04/2012 Legal Notice Date: 06/11/2012 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | T18S., R.11E., Sections 14, 15, and 22 |