The Forest proposes to issue a special use permit to the City of Bend to authorize the City to upgrade the existing Bridge Creek intake facility and replace the aging Bridge Creek water supply pipelines.
Location
West of Bend, Oregon between the City's water intake and outback reservior site. Pipeline route is primarily along FSR 4601 and 4603
Project timeline
1
Scoping Start
12/18/2012
2
Comment Period
04/10/2013
3
Objection Period Start
07/26/2013
4
Decision
11/2013 (Estimated)
5
Implementation
01/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| DN/FONSI Special Use Permit City of Bend Bridge Creek Water Supply System | Decision Signed Date: 11/04/2013 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |