The project would renew expired special use permit(s). This action is needed to make authorizations current and ensure complaince with Forest Service regualtions.
Location
The proejct is located on the Sisters Ranger District.
Project timeline
1
Scoping Start
01/07/2013
2
Decision
07/2013 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Reissuance of Expired Special Use Permits | Decision Signed Date: 07/10/2013 Legal Notice Date: 07/14/2013 |
| Forests | Deschutes National Forest |
| Districts | Sisters Ranger District |
| Legal Land Description | T15S, R09E, SEC 1; T11S, R11E, SEC 19; and T12S, R09E, SEC 33 &34 |