The purpose of the project is to amend the SUP issued to Three Sisters Backcountry to authorize additional winter Nordic recreation opportunities.
Location
Located on the Sisters and Bend-Fort Rock RD along the Metolius-Windigo Trail
Project timeline
1
Scoping Start
11/14/2013
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Winter Yurt SUP | Decision Signed Date: 07/03/2014 |
| Three Sisters Backcountry, Inc, Winter Ski Hut Expansion | Decision Signed Date: 07/03/2014 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District; Sisters Ranger District |
| Legal Land Description | Trail: T17S R9E Sections 11-13,24, 25, 34-36; T18S R9E Section 3,4,9, 16, 17, 20, 21; Yurt: T17S, R9E Sections 11, 34. |