Project is to lease/construct a building for the COIDC at the Redmond Air Center. The analysis will not be subject to FS notice, comment and objection regs. because the activities will not be implementing a decision under a Land & Resource Mgmt Plan
Location
Leased building will be located at Redmond Air Center, Redmond, OR on land owned by the city and leased to the Deschutes National Forest
Project timeline
1
Scoping Start
04/16/2015
2
Decision
06/2015 (Estimated)
3
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Central Oregon Interagency Dispatch Center Decision Notice | Decision Signed Date: 06/10/2015 |
| Forests | Deschutes National Forest |
| Districts | Redmond Air Center |
| Legal Land Description | Not Applicable |