Decision Memo Completed

Metolius Windigo Trail Reconstruction

Deschutes National Forest Deschutes, Oregon Sisters Ranger District

The project would reroute about 1,000 feet of trail to ensure visitor safety and address resource concerns. The 2012 Pole Creek fire created a boggy section of trail which is unsafe for visitor travel.

Location

T16S; R09E; sections 2, 3, 10, and 11. The project is near Forest Road 1514 and the Metolious Windigo trail junction.

Project timeline

1
Scoping Start
04/22/2015
2
Decision
07/2015 (Estimated)
3
Implementation
09/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
Metolius Windigo Trail ReconstructionDecision Signed Date: 07/21/2015
ForestsDeschutes National Forest
DistrictsSisters Ranger District
Legal Land DescriptionNot Applicable