Central Electric Cooperative Inc. is proposing to install 6 vaults and 1.3 miles of buried distribution powerline to replace an existing deteriorating line along SW Suttle Sherman Road.
Location
The proposed location of this project is in T. 13 S., R.8 E., Section 24 and T. 13 S., R 9 E., Section 19 W.M, along the Suttle-Sherman Road
Project timeline
1
Scoping Start
05/15/2015
2
Decision
05/2015 (Estimated)
3
Implementation
09/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| CEC Suttle-Sherman Line Replacement Project | Decision Signed Date: 05/21/2015 |
| Forests | Deschutes National Forest |
| Districts | Sisters Ranger District |
| Legal Land Description | Not Applicable |