Renew communications use lease for existing facilities at Antelope Communications Site at Pine Mountain. No new facilities or ground disturbing activities are authorized.
Location
in NW1/4 Section 25, T. 20 S. R. 15 E., Willamette Meridian at approximately Latitude 43° 48%u2019 40%u201D North, Longitude 120° 52%u2019 47%u201D West. FS160
Project timeline
1
Scoping Start
10/02/2015
2
Decision
11/2015 (Estimated)
3
Implementation
12/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Communications Use Lease Renewals for facilities at Antelope Comm. Site. | Decision Signed Date: 11/09/2015 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |