The proposed maintenance project involves replacement of deteriorating wood poles and associated structural/electrical components. Existing wood poles will be mechanically removed from the ground. Replacement wood pole will be in-kind.
Location
BPA LaPine-Chillquin Transmission Line ROW, Crescent Ranger District; T. 25 S, R. 9 E Sections 29, 31, & 36; T. 26 S, R. 8 E Sections 1, 2, 11, 15, 21, & 32
Project timeline
1
Scoping Start
06/02/2016
2
Decision
08/2016 (Estimated)
3
Implementation
08/2016 (Estimated)