BPA is proposing to replace 12 deteriorating poles inside of its existing 125' ROW along the Pilot Butte-La Pine Transmission Line
Location
Township 18S/ Range 12E/ Section 34 Township 20S/ Range 12E/ Section 6 Township 20S/ Range 11E/ Sections 12, 23, 34 Township 21S/ Range 11E/ Sections 5, 17, 20, 34
Project timeline
1
Scoping Start
04/17/2017
2
Decision
04/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| BPA 2017 Pole Replacement Project Pilot Butte-La Pine Transmission Line | Decision Signed Date: 04/20/2017 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |