the replacement of eleven existing CEC poles. In 2016, all poles in the Camp Sherman area were visually inspected and tested for structural integrity. Eleven of the poles failed the pole test inspection process.
Location
T. 12 S., R. 9 E., SECTIONS 23 & 26, AND T 13 S., R. 9 E., SECTIONS 3, 10, 15
Project timeline
1
Scoping Start
05/01/2017
2
Decision
05/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| CEC Camp Sherman Pole Replacement Project | Decision Signed Date: 05/02/2017 |
| Forests | Deschutes National Forest |
| Districts | Sisters Ranger District |
| Legal Land Description | Not Applicable |