The CRD is considering BPAs request to replace power poles across the Crescent Ranger Districtto ensure the reliability of their transmission lines
Location
Along the 230-kV LaPine-Chiloquin No. 1 Corridor as it crosses the Crescent Ranger District
Project timeline
1
Scoping Start
06/2017 (Estimated)
2
Decision
07/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Deschutes National Forest |
| Districts | Crescent Ranger District |
| Legal Land Description | Not Applicable |