The Crescent Ranger District is considering Midstate Electrics proposal to clear unwanted vegetation in and adjacent to the transmission line corridors and access roads (their current right-of-way) along Highway 58 near Crescent & Odell Lakes
Location
Along Highway 58 near Crescent and Odell Lakes. T24S, R7E, Section 6, 17, 20, and T23S, R7E, Sections 25 and 36,
Project timeline
1
Scoping Start
05/04/2018
2
Decision
06/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| 2018 Midstate Electric Right-of-way Clearing DM | Decision Signed Date: 06/21/2018 |
| Forests | Deschutes National Forest |
| Districts | Crescent Ranger District |
| Legal Land Description | Not Applicable |