The project proposes to restore the hydrologic function of a section of Paulina Creek. A small section of a built steam berm would be removed and the stream channel restored to it natural location.
Location
Paulina Creek near Ogden Group Campground/Peter Skene Trailhead.
Project timeline
1
Scoping Start
11/06/2019
2
Decision
01/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Paulina Creek Restoration | Decision Signed Date: 01/24/2020 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |