TDS Broadcasting LLC (TDS) is proposing to install fiber optic cable to service Gas Transmission Northwest (GTN)to provide high speed data network for GTN facilities located at Compressor Station 12.
Location
Proposed activity would take place southwest of Sugar Pine Butte, near Highways 97. Legal location is T 20S, R 11E, Sections 20, 21, 28, 29.
Project timeline
1
Scoping Start
04/30/2021
2
Decision
06/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| TDS Broadband LLC Fiberline to Gas Transmission Northwest Special Use Permit | Decision Signed Date: 06/29/2021 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |