Decision Memo Completed

2021 Midstate Electric Pole Replacement

Deschutes National Forest Klamath, Oregon Crescent Ranger District

Midstate Electric Cooperative, Inc. proposes replacement of four deteriorating electric transmission line poles along approximately 2.5 miles of Forest Service roads 5825-180 and 9651-260.

Location

The project is located west of Highway 58 approximately 10 miles southwest of Crescent, Oregon, along approximately 2.5 miles of Forest Service roads 5825-180 and 9651-260.

Project timeline

1
Scoping Start
08/11/2021
2
Decision
09/2021 (Estimated)
3
Implementation
10/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
2021 Midstate Electric Pole ReplacementDecision Signed Date: 09/28/2021
ForestsDeschutes National Forest
DistrictsCrescent Ranger District
Legal Land DescriptionT26S, R8E, Sections 6, 7, 8 and 17, Willamette Meridian
Special use management