Environmental Assessment Completed

Campground Expansions

Deschutes National Forest Deschutes, Oregon Bend/Fort Rock Ranger District

This project proposes to analyze effects of increased use at Rock Creek and Gull Point Campgrounds addressing the effects of recreation use on the facilities, character and function at these two sites in regards to past, present and future use.

Location

High Cascade Lakes

Project timeline

1
Scoping Start
06/01/2003
2
Comment Period
02/23/2004
3
Decision
05/2004 (Estimated)
4
Implementation
06/2004 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management
Campground Expansions Project Environmental AssessmentDecision Signed Date: 05/05/2004
ForestsDeschutes National Forest
DistrictsBend/Fort Rock Ranger District
Legal Land DescriptionT21S, R7E, S12; T21S, R8E, S34