This project would authorize Midstate Electric Cooperative to replace two damaged power poles east of Crane Prairie Reservoir to maintain electrical safety and integrity.
Location
The project location is approximately 1.5 miles east of Crane Prairie Reservoir
Project timeline
1
Scoping Start
03/17/2022
2
Decision
04/2022 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Midstate Electric Cooperative Cultus Lake Pole Replacements | Decision Signed Date: 04/13/2022 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | T20S R8E Sections 26 and 35 |