The owners of J7 are requesting to excavate and remove the old foundation and install a new stem wall and concrete footings for the foundation and removal and replacement of the stone chimney with logs. Contractors would conduct the work.
Location
The project area is located on the north shore of Elk Lake and is approximately 32 miles southwest of Bend, OR.
Project timeline
1
Scoping Start
06/03/2024
2
Decision
06/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Elk Lake Cabin J7 Foundation and Chimney Project | Decision Signed Date: 06/20/2024 |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Township 18 South; Range 8 East; Section 29 |