This project proposes the removal of the Edison Shelter near Edison Sno-Park. The existing snow shelter is in disrepair and needs to be removed and replaced with a new structure in a more accessible and fire defensible area nearby.
Location
Township 19 South Range 9 East Section 14
Project timeline
1
Scoping Start
09/24/2024
2
Decision
11/2024 (Estimated)
3
Implementation
12/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Deschutes National Forest |
| Districts | Bend/Fort Rock Ranger District |
| Legal Land Description | Not Applicable |