Environmental Assessment Completed

Fall

Deschutes National Forest Deschutes, Oregon Bend/Fort Rock Ranger District

Proposes vegetation treatments including thinning and final removal of overstory lodgepole pine. Includes fuels reduction in the wildland-urban interface and road closures.

Location

Bend-Redmond

Project timeline

1
Scoping Start
07/01/2002
2
Comment Period
05/18/2004
3
Decision
05/2004 (Estimated)
4
Implementation
01/2004 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Scenery Management; Timber Sales (Green)
Fall Environmental AssessmentDecision Signed Date: 05/18/2004 Legal Notice Date: 05/18/2004
ForestsDeschutes National Forest
DistrictsBend/Fort Rock Ranger District
Legal Land DescriptionT20S, R9E/10E; T21S, R9E
Forest productsFuels managementRoad management