Decision Memo Completed

26. Miller Creek Lamprey Barrier Removal

Fremont-Winema National Forest Klamath, Oregon Chemult Ranger District

The project would remove a barrier originally created to prevent re-establishment of lamprey in Miller Lake.

Location

Approximately ? mile downstream from the outlet of Miller Lake.

Project timeline

1
Scoping Start
06/15/2005
2
Decision
09/2005 (Estimated)
3
Implementation
09/2005 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecies Habitat Improvements
Miller Lake Lamprey Barrier RemovalDecision Signed Date: 09/12/2005
ForestsFremont-Winema National Forest
DistrictsChemult Ranger District
Legal Land DescriptionT27S, R6.5E, Section 19
Wildlife, fish, rare plants