Decision Memo Completed

34 - PacifiCorp(PPL) 230 KV Powerline Permit Reissuance

Fremont-Winema National Forest Klamath, Oregon Chiloquin Ranger District

PPL has applied to reauthorize the permit for "Line 52", 19.5 miles by 125" ROW for power transmisssion. Line was originally authorized by the BIA in 1951

Location

Chiloquin Ranger District, north to south powerline, from near Oaxkanee Overlook south to near Dry Lakes

Project timeline

1
Scoping Start
07/12/2006
2
Decision
07/2006 (Estimated)
3
Implementation
09/2006 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Pacificorp (PPL) 230 KV Powerline Permit IssuanceDecision Signed Date: 07/27/2006
ForestsFremont-Winema National Forest
DistrictsChiloquin Ranger District
Legal Land DescriptionTownships 33, 34, 35, and 36 S, Ranges 7 and 8 E
Special use management