PPL has applied to reauthorize the permit for "Line 52", 19.5 miles by 125" ROW for power transmisssion. Line was originally authorized by the BIA in 1951
Location
Chiloquin Ranger District, north to south powerline, from near Oaxkanee Overlook south to near Dry Lakes
Project timeline
1
Scoping Start
07/12/2006
2
Decision
07/2006 (Estimated)
3
Implementation
09/2006 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Pacificorp (PPL) 230 KV Powerline Permit Issuance | Decision Signed Date: 07/27/2006 |
| Forests | Fremont-Winema National Forest |
| Districts | Chiloquin Ranger District |
| Legal Land Description | Townships 33, 34, 35, and 36 S, Ranges 7 and 8 E |