Non-commercial understory thinning to serve as pretreatment for underburning (associated with Stateline Underburn) and to reduce overstocked conditions. Approximately 1,300 acres.
Location
Lakeview Ranger District
Project timeline
1
Scoping Start
10/16/2003
2
Decision
04/2004 (Estimated)
3
Implementation
05/2004 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| 003.Stateline Pretreatment Thinning | Decision Signed Date: 04/28/2004 |
| Forests | Fremont-Winema National Forest |
| Districts | Lakeview Ranger District |
| Legal Land Description | T40S, R16E, T41S, R15, 16, & 17E |