Map 34. Construct three water holes on the Privy Springs Grazing Allotment using a backhoe or small excavator.
Location
Privy Springs Grazing Allotment southwest of Bly, OR
Project timeline
1
Scoping Start
02/14/2008
2
Decision
06/2008 (Estimated)
3
Implementation
06/2008 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Privy Spring Water Improvement Project | Decision Signed Date: 06/06/2008 |
| Forests | Fremont-Winema National Forest |
| Districts | Bly Ranger District |
| Legal Land Description | T38S, R14E sections 7 and 18, W.M. |